PROGRESS REPORT- JULY 16, 2024
DESIGN/ PROCUREMENT
- The permit drawing set has been completed and is being prepared for submission to the City of Denver
- Our design team will continue to progress the drawings through the month of July, working towards issuing a construction drawing set by the end of the month
- Our construction manager is using the permit set to further develop the project budget and they will utilize the construction set to bid out subcontracts
PERMITTING
- Zoning Use Permit has been approved
- Building and Utility Permit submission is imminent
FIELD UPDATE
- The interior of the existing space has been demolished in accordance with the intended re-design. The space will stay in this demo’ ed state until we begin with construction (pending permit approvals) in September ’24