PROGRESS REPORT- JULY 16, 2024

DESIGN/ PROCUREMENT

  • The permit drawing set has been completed and is being prepared for submission to the City of Denver
  • Our design team will continue to progress the drawings through the month of July, working towards issuing a construction drawing set by the end of the month
  • Our construction manager is using the permit set to further develop the project budget and they will utilize the construction set to bid out subcontracts

PERMITTING

  • Zoning Use Permit has been approved
  • Building and Utility Permit submission is imminent

FIELD UPDATE

  • The interior of the existing space has been demolished in accordance with the intended re-design. The space will stay in this demo’ ed state until we begin with construction (pending permit approvals) in September ’24