PROGRESS REPORT- March 1st, 2025
DESIGN/ PROCUREMENT
- Procurement/ awards to subcontractors by the construction manager Shawut continues.
- Finalization of the interiors and color palette continues.
- The furniture, fixture and equipment components are being managed and acquired and managed by Oak View Group and are ongoing.
PERMITTING/INSPECTION
- The City and County of Denver has provided the permit for the construction of the restaurant to Oak View Group.
- Shawmut Construction has obtained the permit. A copy of this will be placed at the project site.
- Inspection Services are being initiated.
CONSTRUCTION PHASE
- A kick-of meeting was held 27 February with OVG, Shawmut ,and Perkins and Will
- An additional meeting was held on 27 February with Mark Van Loucks to discuss site logistics
- Shawmut is preparing a Site Logistics Plan that will be in place for the duration of the project.
- Mobilization by Shawmut will occur on 10 March by Shawmut.
- Minor additional demolition will occur after 10 March.
- Shawmut will mobilize subcontractors After 10 March for field measurements, and coordinate material deliveries to begin installation.
- Ongoing coordination work with building management has begun and will be in place for the duration of the project.