PROGRESS REPORT-

March 1st, 2025

DESIGN/ PROCUREMENT

  • Procurement/ awards to subcontractors by the construction manager Shawut continues.‍

  • Finalization of the interiors and color palette continues.

  • The furniture, fixture and equipment components are being managed and acquired and managed by Oak View Group and are ongoing.

PERMITTING

  • The City and County of Denver has provided the permit for the construction of the restaurant to Oak View Group.

  • Shawmut Construction has obtained the permit.  A copy of this will be placed at the project site.

  • Inspection Services are being initiated.

FIELD UPDATE

  • A kick-of meeting was held 27 February with OVG, Shawmut ,and Perkins and Will

  • An additional meeting was held on 27 February with Mark Van Loucks to discuss site logistics

  • Shawmut is preparing a Site Logistics Plan that will be in place for the duration of the project.

  • Mobilization by Shawmut will occur on 10 March by Shawmut.

  • Minor additional demolition will occur after 10 March.

  • Shawmut will mobilize subcontractors After 10 March for field measurements, and coordinate material deliveries to begin installation.

  • Ongoing coordination work with building management has begun and will be in place for the duration of the project.