Selective Demolition near complete, MEP demolition on-going
Layout is on-going
Framing of metal stud walls and soffit is in progress
Pilot holes and coring for the plumbing and electrical scope began this week and will be on-going for the weeks to come
Parking spaces required to be vacated have been coordinated by Fred and Paul; caution tape has been installed to block off spaces
Coring is beginning on the club side of the space, goal is to turn spaces back to the Landlord as quickly as possible
Overhead and in-wall plumbing and electrical is in progress and will be on-going for weeks to come
Removal of ductwork and install of new is in progress
Communication with Denver’s 811 Dig Safe has begun to coordinate safe removal of existing concrete and grease interceptor
Upon survey and results, demolition and excavation will begin
Dumpsters will be reduced to just a single unit
As a friendly reminder, any persons who enter the jobsite must wear the required PPE whether it is during or after construction hours. For any non-subcontractors, it is preferred that Fred is notified of the visit ahead of time and that said visitors meet Fred at the field office entry door which is off the parking lot. This will assure the appropriate PPE is worn or provided.