PROGRESS REPORT

July 1st, 2025

  • Coring – for plumbing and electrical scope

  • Under slab work in Parking garage – electrical and plumbing

  • HVAC – removal of existing AHUs, ductwork throughout

  • Drywall – framing of walls, soffits, ceilings

  • Electrical – rough-in ceiling and walls

  • Plumbing – rough-in at bars and BOH

  • FSE – Walk-in Freezer install

  • Fire Sprinkler - demo and rough-in

  • Fire Alarm – complete remaining demo, rough-in

  • MEP Inspections

  • Start drywall Installation