PROGRESS REPORT

May 1st, 2025

On-going and upcoming work for Penterra Plaza Restaurant.

  • Grease Interceptor – installation of new trap along with plumbing lines and connections associated (Fred and I will schedule a coordination meeting with Mark, Shawn, and Paul regarding schedule, logistics, etc. prior to starting work)

  • Plumbing – finalize additional core locations required, continue interior plumbing runs and infill of unused cores.

  • Electrical – continue wall and ceiling rough-ins

  • Mechanical – continue running ductwork

  • Fire Alarm – begin rough-in layout

  • Fire Sprinkler – begin rough-in layout, coordinate with Paul/base building

  • Continue Inspections